GET IN TOUCH:

Minot, North Dakota

1907 17th St SE

Minot, ND 58701

701.837.8737

Williston, North Dakota

3210 27th St W

Suite 200

Williston, ND 58801

701.577.4127

  • Facebook icon
  • Twitter icon
  • LinkedIn icon
  • Instagram icon

Boise, Idaho

7661 West Riverside Dr

Suite 102

Garden City, ID 83714

208.853.6470

Ackerman Surveying

Minot, ND

701.838.0786

Williston, ND

701.577.4127

CONTACT US:

TRANSPORTATION

WATER RESOURCES

MUNICIPAL

CONSTRUCTION ENGINEERING

SURVEYING

DISCIPLINES INVOLVED

MINOT, ND

6th street UNDERPASS AND PUMP STATION project

Beginning in 2006, Ackerman-Estvold worked closely with the City of Minot to develop a project that would address recurrent flooding at the 6th Street Underpass, adjacent to the Minot Public Library and City Hall. Existing systems designed to convey the runoff from the approximately 160-acre urban watershed were grossly undersized. During the detailed analysis of existing conditions, it was also determined that adjacent storm sewer systems along 3rd Street Southeast (east of the project site) and Burdick Expressway (west of the project site) were undersized as well, contributing to the problem.

 

Ackerman-Estvold engineers designed a storm water management system that addressed all three concerns.  By extending storm sewers into the uplands of the watershed, the developed areas contributing to the 3rd Street Southeast and Burdick Expressway storm sewers were effectively reduced, thereby reducing the peak flows within those systems and allowing the existing systems to operate as intended. Additionally, by capturing runoff within the uplands of the watershed, the system was designed to allow the upland runoff to be directly conveyed under pressure to the Mouse River, thereby eliminating the need to pump this runoff and significantly reducing the required size of the pump station. The reduced size pump station is a 975 horsepower triplex pump system with capacity to pump 40,000 gallons of storm water per minute.

 

Over the next handful of years following the initial analysis, the project remained idle due to both funding constraints and the historic 2011 Mouse River Flood. The project began to move forward again in 2012 with some re-evaluation of previous work and design of the project plans and specifications.

 

In addition to the extensive storm water upgrades, the 6th Street Underpass project included the reconstruction of approximately four blocks of concrete pavement, intersection alignment improvements, modifications to adjacent roadways including Burdick Expressway, water and sewer modifications, traffic signals, sidewalks, and lighting.

 

Our team was responsible for the design of this monumental project for the City of Minot and performed the construction engineering on the project in accordance with NDDOT practices.  The $4.8 million roadway and storm sewer portions of the project were completed in 2014. The storm water pump station was completed in 2016 at a cost of $4.4 million.  The construction of the project was completed in a closely coordinated effort between multiple independent contractors, the City of Minot, the NDDOT, Ackerman-Estvold and several residents and businesses in the project area.

 

Following our work on this project, our team remained interested in improving the area for the public. In 2016 Ackerman-Estvold volunteers stained and sealed the stamped concrete adjacent to the sidewalks as a part of a beautification project for the Magic Day of Giving.